Denham Wind Turbine Replacement Project

The Wind Turbine Generation Replacement Project aims to replace aging wind turbines to maintain and enhance renewable energy contributions, ensuring a reliable power supply and supporting decarbonisation goals in Denham.

What's happening now?

The project has now progressed into the next phase. After detailed technical, environmental, financial and community assessments, we’ve identified a like-for-like replacement of the existing wind generation capacity as an option. This option aligns with community expectations to retain wind generation while supporting a reliable and cost-effective renewable energy future. 

Current activities include procurement planning, detailed design and network studies, environmental approvals, and ongoing community and stakeholder engagement.

Community collaboration

We’re using Horizon Power’s Future Energy Framework to work closely with local residents, Traditional Owners, businesses, and government agencies to design solutions that reflect Denham’s unique character and aspirations.

This includes considering land access, heritage factors and the broader vision for the Gascoyne region’s clean energy future.

We'd love to hear from the Denham community - please get in touch if you have any feedback on this project.

Tab content 1

Frequently asked questions

collapse icon

Much of the current work is happening behind the scenes as we undertake detailed technical, environmental, financial and community assessments. Horizon Power will then commence a Request for Tender process to identify a preferred solution. Subject to procurement outcomes and regulatory approvals, the wind turbine replacement project is expected to take approximately three years to complete.

collapse icon

Yes. The wind turbines are fully integrated into Denham’s standalone microgrid, which supplies power exclusively to the local community. The wind turbines do not export energy to other towns and are dedicated to helping meet Denham’s energy needs.

collapse icon

Denham’s wind turbines were installed in 1997–98 and are nearing the end of their operational life. With one turbine already out of service and another close to this point, replacement is needed to maintain reliable supply for the community. 

Horizon Power considered refurbishment and replacement options and determined that modern replacement technology provides the most practical long-term solution to retain renewable generation in Shark Bay. 

collapse icon
Yes, the new turbines planned for Denham are expected to be more efficient than the existing ones. Overall, the replacement of Denham's wind turbines is anticipated to bring about increased efficiency and reliability, contributing to the town's sustainable energy future.
collapse icon

Replacing Denham's ageing wind turbines will help maintain wind generation as part of the town's power system into the future. The project is also an opportunity to assess modern turbine technology that is suitable for Denham's unique operating environment and future energy needs.   

collapse icon

We're currently exploring the feasibility of recycling components from the existing turbines, including assessing which parts can be recycled, identifying the nearest suitable recycling facilities, and evaluating the costs involved. 

Tab content 1

What's happening and when?

Here's a high level timeline of what to expect, subject to change as the project progresses.

01

2024 to mid-2025

Project scoping and feasibility

This first phase involved identifying the need to replace Denham's ageing wind turbines and assessing potential future energy system pathways.

02

October 2025 to mid-2026

Project planning and market engagement

Phase 2 of the project involves undertaking community engagement activities and preparing for an Expression of Interest (EOI) process to identify potential technology solutions and delivery partners.

03

Mid-2026 to mid-2027

Request for Tender (RFT)

In Phase 3, we’ll invite detailed proposals through a Request for Tender. This will help us assess the most suitable wind generation technology and delivery model for Denham's needs.

04

Late 2027

Business case and approvals 

A business case, including the recommended technology and delivery pathway, will be presented to Horizon Power’s Executive and Board, followed by submission to government authorities for approval. We expect to share a construction timeline by the end of 2026, pending all required approvals.

05

2027 to 2028

Project delivery

Once approved, we’ll move into the design, construction and installation phase. This will include replacing the ageing turbines and integrating the new system with Denham's existing energy infrastructure.

06

Early 2030

Project completed

The upgraded wind generation system will be operational—helping to deliver cleaner, more reliable energy and supporting Denham's transition to a more sustainable future.